EngineAutos / Power & Compute Research

BECO–Firehouse 230 kV

Research index · Project directory · Methodology

Dominion proposes two 230 kV lines linking the existing BECO substation with the planned Firehouse substation in Loudoun County, Virginia. Two official sources carry different schedule statements. Their scope and milestones have not been established as equivalent.

Record checked: 2026-11-11. Evidence status: official planning sources verified; cross-source scope unresolved. Operating status: UNKNOWN; no verified energization or delivered-power evidence in this record.

Identity and scope

  • Internal project ID: PRJ_US_VA_LOU_BECO_FIREHOUSE. This is an EngineAutos research identifier, not an official queue number.
  • PJM need: DOM-2024-0016. Virginia SCC case: PUR-2026-00062.
  • Location: Loudoun County, Virginia, United States.
  • Dominion scope: two proposed BECO–Firehouse 230 kV lines. PJM scope: Firehouse delivery, including a proposed four-breaker 230 kV ring bus and cut/extension of Line #2207. Do not assume those descriptions cover identical work.

Fact record

FactValue / unitAs of / scopeSource / evidence status
Voltage230 kVProposed line scope; source checked 2026-11-11S1 • utility proposal
Line count2 linesBECO to Firehouse; source checked 2026-11-11S1 • proposed
Line-service forecastEarly 2029Dominion line-service milestone; forecast, not confirmed CODS1 • utility forecast; original publication date UNKNOWN
Firehouse delivery date2030-12-31PJM project schedule in April 2026 meeting deckS2 p. 12 • planning forecast
Engineering stageEngineeringPJM April 2026 meeting deckS2 p. 12 • source-stated planning status
Initial summer demand209 MWInitial summer-load forecast; year not established in this recordS2 p. 11 • demand forecast, not delivered power
2030 summer demand234 MW2030 forecast horizonS2 p. 11 • demand forecast, not delivered power
Delivered powerUNKNOWN MWNo verified operational delivery evidenceUNKNOWN
Operational IT capacityUNKNOWN MWNo verified IT-capacity evidenceUNKNOWN
Confirmed final CODUNKNOWNFinal commercial-operation date not establishedUNKNOWN
Comparable schedule driftUNKNOWNSame-scope, same-milestone comparison not establishedUnresolved; no delay conclusion

What changed in this release

2026-11-11: this permanent project record was first published. The two schedule statements are shown separately, and forecast load is separated from delivered capacity. No project-delay event is asserted.

What to check next

A same-scope milestone mapping, the applicable SCC order or filing, and direct energization or operating evidence would be needed to resolve the schedule and operating fields. These are evidence gaps, not claims that work is late or has stopped.

Sources and dates

  • S1: Dominion Energy, BECO–Firehouse. Project Details, Timeline and Legal. Publication date: UNKNOWN. Checked: 2026-11-11. The Legal section supports the SCC case reference; a published response deadline does not prove a response was filed.
  • S2: PJM, Dominion Supplemental Projects. Relevant pages: 11–12. Meeting date: 2026-04-07. Original posting: 2026-03-26, according to revision history p. 15. Checked: 2026-11-11.
  • Detailed SCC-PDF claims are excluded from this release because the original PDF could not be retrieved reliably during review.

中文摘要

项目ID:PRJ_US_VA_LOU_BECO_FIREHOUSE。Dominion提出两条BECO至Firehouse的230千伏线路,并预计2029年初投入服务。PJM文件对Firehouse供电项目列出2030年12月31日。两个来源的工程范围和里程碑是否一致尚未确定,不能据此认定延期。209兆瓦与234兆瓦是负荷预测,不是已交付电力;已交付电力和运行中IT容量均为UNKNOWN。

证据核查日期:2026年11月11日。完整事实、来源及限定条件见本页英文记录。

ملخص بالعربية

معرّف المشروع: PRJ_US_VA_LOU_BECO_FIREHOUSE. تقترح Dominion خطين بجهد 230 كيلوفولت بين BECO وFirehouse، وتتوقع دخولهما الخدمة في أوائل 2029. تسجل وثيقة PJM تاريخ 31 ديسمبر 2030 لمشروع إمداد Firehouse. لم يُثبت تطابق نطاق العمل والمرحلة المقصودة بين المصدرين، لذلك لا يثبت هذا الفرق وجود تأخير. القيمتان 209 و234 ميغاواط هما توقعات للطلب وليستا قدرة مُسلّمة. القدرة المُسلّمة وقدرة تقنية المعلومات التشغيلية مسجلتان على أنهما UNKNOWN.

تاريخ مراجعة الأدلة: 11 نوفمبر 2026. يتضمن السجل الإنجليزي في هذه الصفحة التفاصيل الكاملة والمصادر والقيود.

Related: Data sources · Corrections · Research contact

EngineAutos / Power, Compute & Applied AI
Source-linked research. Coverage is selective. Review date: 11 November 2026.
Unknown means not established, not zero. No live telemetry or investment advice.

About · Methodology · Data sources
Corrections · Contact

EVIDENCE RESEARCH WORKSPACE

Type a question. Follow the facts.

SOURCE-DATED SNAPSHOT
Last record checks: 11 Nov 2026

Search 100 archived records and 262 prepared questions. Open the evidence, compare records, and follow the next check. No live AI answers. Hourly website sync is not connected.

This research tool matches text in your browser, without sending it to an AI service or storing your query. Do not enter confidential data. External links open the source website.
How to research here
  1. Search a name or topic, then open a matching prepared question. A match is a reference, not proof that your question’s premise is true.
  2. Check the event date, source publication date and record review date separately. Planned, testing and operating are not interchangeable.
  3. Select up to three records to compare evidence, limits and sources. Download a plain-text research brief if useful.

Coverage is selective. There is no live telemetry, automated investment recommendation or guaranteed current availability. Dates below are stored review dates, not an hourly refresh indicator. Your comparison and browsing trail disappear when this page closes or reloads.

Evidence research